Kossino-Ukhtomskaya - Saltykovskaya Street - Kossino Section of the Kozhukhovskaya Line
Subway / Kossino-Ukhtomskaya - Saltykovskaya Street - Kossino Section of the Kozhukhovskaya Line

Building the Kossino-Ukhtomskaya - Saltykovskaya Street - Kossino section of the Moscow Subway Kozhukhovskaya Line.

The work started in 2013 and is to be completed in 2015.

Length of the facilities:

  • Left stage tunnel between the Kossino-Ukhtomskaya and - Saltykovskaya Street stations - 1,075.2 m;
  • Right stage tunnel between the Kossino-Ukhtomskaya and Saltykovskaya Street stations- 1,071 m;
  • Left stage tunnel between the Saltykovskaya Street and Kossino stations - 1,922.2 m;
  • Right stage tunnel between the Saltykovskaya Street and Kossino stations - 1,874.6 m;
  • Saltykovskaya Street Station facilities - 247.3 m;
  • Kossino Station facilities - 194.6 m;
  • Right stage tunnel of a section from the Kossino Station to the exist chamber - 665 m;
  • Left stage tunnel of a section from the Kossino Station to the exist chamber - 672 m;
  • Branch tunnel connecting to the Tagansko-Krasnopresnenskaya line - 745 m.

Scope of Operations:

  • Building 4 stage tunnels;
  • Building the Saltykovskaya Street and Kossino stations (foundation pit excavation, erection of major reinforced concrete structures, internal station civil work, backfilling, and area improvement);
  • Station facility and stage tunnel permanent installations and outfitting;
  • Building three tunnel ventilation facilities and two drainage plants;
  • Building a connecting branch line between the Tagansko-Krasnopresnenskaya and Kozhukhovskaya lines.

The stage tunnels will be shield driven from the Kossino-Ukhtomskaya Station via the Saltykovskaya Street and Kossino stations terminating at the exit chamber downstream the Kossino Station. The tunneling will be done using the Herrenknecht-6150 and Robbins-371 tunnel-boring machines.

The branch tunnel connecting the Tagansko-Krasnopresnenskaya line to the Kozhukhovskaya line will be driven using the Herrenknecht-6150 Tunnel-Boring Machine.

The basic structural members to be used for building the stage tunnels are prefabricated reinforced concrete blocks with the inside diameter of 5.4 meters.

The station facilities are built by the open-pit method. The Saltykovskaya Street and Kossino stations are located 19 to 21 meters deep underground. Each station will have underground lobbies connected to the platforms by flights of stairs, escalators and also by elevators for disabled passengers.

The Kossino Station will have an arrangement for transfer to the Lermontovsky prospekt Station of the Tagansko-Krasnopresnenskaya subway line.



  • Vykhino — Lermontovsky Prospekt Section in Moscow
  • Lermontovsky Prospekt — Zhulebino Section in Moscow
  • Zhulebino - Kotelniki Section in Moscow
  • Kossino-Ukhtomskaya — Nekrasovka Section in Moscow
  • Kossino-Ukhtomskaya - Saltykovskaya Street - Kossino Section of the Kozhukhovskaya Line