Main
Feedback
Map
Русский
     
Main

Video


08.06.2010 — Сombined road Adler – Krasnaya Polyana is 25% complete

Сombined road Adler – Krasnaya Polyana is 25% complete by beginning of August.


Страницы: 1 | 2 | 3 | 4 | 5 | 6 | 7
Архив по годам: 2009; 2010;
 
 
Railway Bridge over the Shaldura River
Railway construction / Railway Bridge over the Shaldura River

Railway Bridge over the Shaldura River is located at KP 6712 km of the I-st and II-nd tracks of the Ulyakan to Uryum Section of the Transbaikal Railway.
Start of works: January 2008; completion of works: November 2008.

Bridge design: 3 × 12 m.
The project includes: replacement of all bridge span structures, repair of abutments and intermediate pillars.
Dismantling of spans is carried out by transverse rolling technology with subsequent dumping by tractors. Middle spans are installed by two NK-450 cranes from ground. Ending spans are installed by the Sokol railway crane and NK-450 crane from ground.

While performing the works two span structures 0-1 and 1-2 along the even track are installed and abutments at the odd and even tracks have been repaired.



  • Combined motor and rail road Adler – Krasnaya Polyana
  • Bridge across the Zeya River
  • Bridge across the Buzan River
  • Bridge across the Volga River (Ulyanovsk)
  • Bridge across the Kama River
  • Bridge across the Moscow River
  • Bridge across the Vyatka River
  • Bridge across the Unzha River
  • Bridge across the Volga River (Zelenodolsk)
  • Bridge across the Don River
  • Bridge across the Ob River
  • Bridge across the Prokhladnaya River
  • Viaduct at the Agryz – Druzhynino
  • Railway Bridge over the Shaldura River
  • Construction of the second track
  • Small artificial structures
  • Bridge across the Oka River
  • Moscow, Russia
    www.rusmost.ru
    www.skmost2014.ru
    E-mail: usk@skmost.ru
     
    Сopyright © 2007 SK Most. All rights reserved.  
    Developed by ArtDeneb